Supreme Court allows appeal to establish easement for transmission lines over private land.
Legislator summary
AI generatedThe Supreme Court admitted the cassation appeal to the Civil Chamber for further examination. The applicant sought to establish a transmission easement over the respondent's land, arguing that the lower court's refusal violated property rights and public interest in energy infrastructure. The court decided to proceed with the appeal because the lower ruling required review regarding the balance between private property and public utility needs.
Legislator headnote
AI generatedUstawa o służebnościach; Ustawa o energetyce: The court may admit a cassation appeal to review the establishment of a transmission easement when the lower court's refusal fails to adequately balance private property rights with public interest in energy infrastructure.
Keywords
AI generatedCited Legislation
AI generatedFull text
Sygn. akt V CSK 502/17 POSTANOWIENIE Dnia 22 marca 2018 r.Sąd Najwyższy w składzie: SSN Bogumiła Ustjanicz w sprawie z wniosku J. K.-B.przy uczestnictwie T. S.A. z siedzibą w K.o ustanowienie służebności przesyłu,na posiedzeniu niejawnym w Izbie Cywilnej w dniu 22 marca 2018 r.,na skutek skargi kasacyjnej wnioskodawczyni od postanowienia Sądu Okręgowego we W.z dnia 13 kwietnia 2017 r., sygn. akt II Ca […], przyjmuje skargę kasacyjną do rozpoznania.