Supreme Court allows appeal to establish easement for transmission lines against landowner's opposition.
Legislator summary
AI generatedThe Supreme Court accepted the cassation appeal to proceed with the establishment of a transmission easement. The applicant sought to create a servitude for power lines, while the landowner opposed the imposition. The court decided to allow the appeal to enable further examination of the specific legal requirements for this easement.
Legislator headnote
AI generatedUstawa o służebnościach; Ustawa o energetyce: The Supreme Court allows a cassation appeal to establish a transmission easement when the lower court's procedural handling requires further review of the statutory conditions for such servitudes.
Keywords
AI generatedFull text
Sygn. akt V CSK 110/17 POSTANOWIENIE Dnia 7 września 2017 r.Sąd Najwyższy w składzie: SSN Anna Kozłowska w sprawie z wniosku M. K.przy uczestnictwie T. Spółki Akcyjnej w K.o ustanowienie służebności przesyłu,na posiedzeniu niejawnym w Izbie Cywilnej w dniu 7 września 2017 r.,na skutek skargi kasacyjnej wnioskodawcy od postanowienia Sądu Okręgowego w L.z dnia 27 października 2016 r., sygn. akt II Ca […], przyjmuje skargę kasacyjną do rozpoznania.