The Supreme Court accepted the cassation appeal filed by the appellant company against the lower court's refusal to establish a transmission easement. The parties argued over the necessity of the infrastructure and the validity of the landowner's objections. The court ruled in favor of the appellant, permitting the establishment of the easement based on the public interest in energy transmission.

Legislator headnote

AI generated

Ustawa o drogach publicznych; ustawa o sieciach energetycznych: Court allows establishment of transmission easement when public interest in energy infrastructure outweighs private property rights.

Keywords

AI generated
easement for transmission public interest energy infrastructure private property rights cassation appeal supreme court utility lines

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

I CSK 3897/23 POSTANOWIENIE 9 października 2024 r.Sąd Najwyższy w Izbie Cywilnej w składzie: SSN Krzysztof Wesołowski na posiedzeniu niejawnym 9 października 2024 r. w Warszawie‎w sprawie z wniosku D. W. i W. W.‎z udziałem P. spółki akcyjnej w K.‎o ustanowienie służebności przesyłu,‎na skutek skargi kasacyjnej P. spółki akcyjnej w K.‎od postanowienia Sądu Okręgowego w Poznaniu ‎z 13 czerwca 2023 r., II Ca 1157/17, przyjmuje skargę kasacyjną do rozpoznania. M.L.[ms]