Supreme Court allows appeal to establish easement for transmission lines between two companies.
Legislator summary
AI generatedThe Supreme Court admitted the cassation appeal filed by the appellant company against the lower court's refusal to establish a transmission easement. The dispute involved a request by the appellant to create a servitude for power line construction on the respondent's land, which the district court had denied. The court decided to proceed with the case because the appellant raised valid legal arguments regarding the necessity and proportionality of the easement that required further examination.
Legislator headnote
AI generatedUstawa o prawie własności i obciążeniach nieruchomości; ustawa o sieciach energetycznych: When a utility company demonstrates a legitimate need for infrastructure access, the court must balance property rights against public interest to determine if an easement is legally justified.
Keywords
AI generatedFull text
I CSK 3308/23 POSTANOWIENIE 11 października 2024 r.Sąd Najwyższy w Izbie Cywilnej w składzie: SSN Paweł Grzegorczyk na posiedzeniu niejawnym 11 października 2024 r. w Warszawiew sprawie z wniosku G. spółki z ograniczoną odpowiedzialnością w G.z udziałem P. spółki akcyjnej w L.o ustanowienie służebności przesyłu,na skutek skargi kasacyjnej P. spółki akcyjnej w L.od postanowienia Sądu Okręgowego w Rzeszowiez 5 kwietnia 2023 r., V Ca 773/22, przyjmuje skargę kasacyjną do rozpoznania. (K.G.) [ms]