Supreme Court allows appeal to establish easement for transmission lines against landowners' objections.

Case Number I CSK 3262/25
Court / Authority
Jurisdiction Poland (PL)
Outcome Partially Allowed

Legislator summary

AI generated

The Supreme Court accepted the cassation appeal filed by W.K. and R.K. against the lower court's refusal to establish a transmission easement. The applicants argued that the public interest in energy infrastructure outweighed their property rights, while the opposing party contended that the proposed route violated their land use rights. The court decided to proceed with the case because the lower court's reasoning on balancing public utility against private property rights required further examination by the full bench.

Legislator headnote

AI generated

Ustawa o drogach publicznych; ustawa o sieciach energetycznych: When public interest in energy infrastructure necessitates land use changes, courts must balance private property rights against the necessity of public utility projects.

Keywords

AI generated
easement for transmission public utility interest property rights balance cassation appeal energy infrastructure

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

I CSK 3262/25 POSTANOWIENIE 16 kwietnia 2026 r.Sąd Najwyższy w Izbie Cywilnej w składzie: SSN Władysław Pawlak na posiedzeniu niejawnym 16 kwietnia 2026 r. w Warszawie‎w sprawie z wniosku W.K. i R.K.‎z udziałem P. spółki z ograniczoną odpowiedzialnością w T.‎o ustanowienie służebności przesyłu,‎na skutek skargi kasacyjnej W.K. i R.K.‎od postanowienia Sądu Okręgowego w Krakowie‎z 8 lipca 2022 r., II Ca 3026/21, przyjmuje skargę kasacyjną do rozpoznania. [PG][SOP]