Supreme Court dismisses appeal on contract breach claim where defendant failed to prove impossibility of performance.
Legislator summary
AI generatedThe Supreme Court of Poland dismissed the cassation appeal filed by the defendant against the appellate court's judgment. The plaintiff sued for payment based on a breach of contract, while the defendant argued that performance became impossible due to specific circumstances. The court rejected the defense because the defendant failed to substantiate the claim of impossibility with sufficient evidence, leaving the original judgment intact.
Legislator headnote
AI generatedKodeks cywilny; Kodeks postępowania cywilnego: When a party claims impossibility of performance, they must prove the objective impossibility; failure to do so results in the rejection of the defense and upholding of the claim.
Keywords
AI generatedCited Legislation
AI generatedFull text
Sygn. akt I CSK 25/21 POSTANOWIENIE Dnia 9 marca 2021 r.Sąd Najwyższy w składzie: SSN Maria Szulc w sprawie z powództwa Centrum B. S.A. w W.przeciwko J. B.o zapłatę,na posiedzeniu niejawnym w Izbie Cywilnej w dniu 9 marca 2021 r.,na skutek skargi kasacyjnej pozwanej od wyroku Sądu Apelacyjnego w (…)z dnia 6 lutego 2020 r., sygn. akt VII AGa (…), odmawia przyjęcia skargi kasacyjnej do rozpoznania.