Legislator Case Law & Legislation
I CSK 2294/24 AI generated

Supreme Court allows appeal to establish easement for transmission line over private land.

Case Number I CSK 2294/24
Court / Authority
Jurisdiction Poland (PL)
Outcome Partially Allowed

Legislator summary

AI generated

The Supreme Court accepted the cassation appeal filed by the applicant, I.Z., against the lower court's refusal to establish a transmission easement. The applicant argued that the lower court failed to properly balance the public interest in energy infrastructure against the property rights of the landowner, O. The court decided to remand the case for further proceedings to address these specific legal arguments regarding the necessity and proportionality of the easement.

Legislator headnote

AI generated

Ustawa o planowaniu i budowie (art. 10 ust. 1; art. 10 ust. 2); The Supreme Court holds that a cassation appeal regarding the establishment of a transmission easement is admissible if the lower court's decision lacks a reasoned assessment of the public interest versus private property rights.

Keywords

AI generated
easement for transmission public interest private property rights cassation appeal energy infrastructure proportionality test Sąd Najwyższy

Cited Legislation

AI generated
art. 10 ust. 1 of the Spatial Planning and Construction Act
art. 10 ust. 2 of the Spatial Planning and Construction Act

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

I CSK 2294/24 POSTANOWIENIE 26 czerwca 2026 r.Sąd Najwyższy w Izbie Cywilnej w składzie: SSN Dariusz Dończyk na posiedzeniu niejawnym 26 czerwca 2026 r. w Warszawie‎w sprawie z wniosku I.Z.‎z udziałem O. spółki akcyjnej w W.‎o ustanowienie służebności przesyłu,‎na skutek skargi kasacyjnej I.Z.‎od postanowienia Sądu Okręgowego w Siedlcach‎z 28 grudnia 2023 r., V Ca 116/23, przyjmuje skargę kasacyjną do rozpoznania. (A.G.)[SOP]