Legislator Case Law & Legislation
III SK 35/07 AI generated

Supreme Court rules Energy Regulator must suspend, not dismiss, consumer energy supply disputes regarding contract termination.

Case Number III SK 35/07
Court / Authority
Jurisdiction Poland (PL)
Decision Date
Outcome Allowed / Granted

Legislator summary

AI generated

The Supreme Court of Poland overturned lower court decisions that dismissed a consumer's complaint about energy supply suspension. The consumer argued the energy company terminated their contract, causing the supply halt, while the regulator claimed the contract was void. The court held that determining the validity of the contract termination is a judicial matter, not an administrative one, and the regulator lacks jurisdiction to dismiss such cases prematurely.

Legislator headnote

AI generated

Art. 6 ust. 3 Prawa energetycznego; Art. 105 k.p.a.: The Energy Regulator cannot dismiss a consumer's claim regarding energy supply suspension if the dispute concerns the validity of the energy supply contract termination, as such issues fall within the jurisdiction of ordinary courts.

Keywords

AI generated
Energy Supply Suspension Contract Termination Validity Regulator Jurisdiction Administrative Dismissal Consumer Protection Law

Cited Legislation

AI generated
Art. 6 ust. 3 Prawa energetyczne
Art. 105 k.p.a.
Art. 5 ust. 1 Prawa energetyczne
Art. 5 ust. 2 pkt 1 Prawa energetyczne
art. 105 k.p

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text