Supreme Court dismisses delay complaint as moot because the lower court already issued a final judgment.

Case Number III SPP 165/05
Court / Authority
Jurisdiction Poland (PL)
Decision Date
Outcome Dismissed

Legislator summary

AI generated

The Supreme Court dismissed the applicant's complaint regarding the excessive length of proceedings before the Court of Appeal in Gdańsk. The applicant argued that the court failed to set a hearing date for over a year, causing significant delay. However, the court ruled that the proceedings were already concluded with a final judgment on December 6, 2005, before the Supreme Court could even hear the complaint. Consequently, the court determined that issuing a decision on the delay was unnecessary and the complaint was without subject matter.

Legislator headnote

AI generated

Art. 355 § 1 k.p.c.; Art. 4 ust. 2 ustawy o skardze na naruszenie prawa strony do rozpoznania sprawy w postępowaniu sądowym bez nieuzasadnionej zwłoki: A complaint against the excessive length of proceedings is inadmissible if the underlying proceedings have already been concluded and the applicant has achieved the purpose of the complaint.

Keywords

AI generated
excessive length of proceedings mootness of proceedings final judgment effect complaint dismissal legal remedy exhaustion

Cited Legislation

AI generated
Art. 355 § 1 k.p.c.
Art. 4 ust. 2 ustawy z dnia 17 czerwca 2004 r. o skardze na naruszenie prawa strony do rozpoznania sprawy w postępowaniu sądowym bez nieuzasadnionej zwłoki
art. 397 § 2 k.p.c
art. 391 § 1 k.p.c
art. 45 ust. 1 Konstytucji RP
art. 355 § 1 k.p.c
art. 355 k.p.c

Cited Case Law

AI generated

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text