Polish Supreme Court allows tariff change due to energy cost increases under Art. 155 of the Administrative Procedure Code.

Case Number III SZP 2/04
Court / Authority
Jurisdiction Poland (PL)
Decision Date
Outcome Allowed / Granted

Legislator summary

AI generated

The Polish Supreme Court resolved a legal question regarding whether rising energy purchase costs justify changing an approved electricity tariff. The court found that administrative approval of a new, higher tariff by the Energy Regulatory Office provided a valid basis for modifying the previous decision under Article 155 of the Administrative Procedure Code. Consequently, the court ruled that such cost increases constitute a legitimate circumstance for altering the tariff to prevent financial loss for the energy company.

Legislator headnote

AI generated

Art. 155 k.p.a.; Art. 155 ust. 1 k.p.a.: An increase in the costs of purchasing electricity and transmission services, resulting from a regulatory decision approving a new tariff with higher rates, constitutes a valid circumstance justifying the change or revocation of a previously issued tariff approval decision.

Keywords

AI generated
Administrative Procedure Code tariff adjustment energy regulatory authority cost increase justification administrative reconsideration public interest balancing energy sector regulation

Cited Legislation

AI generated
Art. 155 k.p.a.
Art. 155 ust. 1 k.p.a.
art. 155 k.p
art. 3 § 2 k.p.c
art. 232 k.p.c
art. 16 k.p
art. 15 k.p
art. 10 Konstytucji

Cited Case Law

AI generated
III CRN 120/91

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text