Simplified procedure in labor law allows multiple claims of same type in one suit even with different due dates.
Legislator summary
AI generatedThe Supreme Court resolved a legal question regarding whether multiple claims of the same type can be pursued in a single lawsuit under simplified labor procedure. The plaintiff sought various monthly bonuses for different years, which the lower court combined into one case despite different due dates. The court ruled that such combination is permissible and that joining separate cases under general procedure rules effectively abandons the simplified procedure regardless of the claim's value.
Legislator headnote
AI generatedArt. 5051-50513 k.p.c.; Art. 476 § 1 k.p.c.; Art. 219 k.p.c.: In simplified labor proceedings, multiple claims of the same type arising from the same factual and legal basis may be pursued in one lawsuit even with different due dates, and joining separate cases under general procedure rules constitutes a de facto abandonment of simplified procedure.