Legislator Case Law & Legislation
III RN 2/99 AI generated

Supreme Court dismisses extraordinary review when administrative order expires, citing statutory time limits and procedural bars.

Case Number III RN 2/99
Court / Authority
Jurisdiction Poland (PL)
Decision Date
Outcome Dismissed

Legislator summary

AI generated

The Supreme Court dismissed the extraordinary review filed by the Minister of Justice against a lower court decision. The underlying administrative order suspending construction work had expired two months prior to the review, rendering it legally void. Consequently, the court held that the review was inadmissible because it sought to overturn a decision that no longer had legal effect.

Legislator headnote

AI generated

Art. 50 ust. 4 Prawa budowlanego; Art. 105 § 1 KPA: An administrative order suspending construction work loses validity after two months, making any extraordinary review challenging such an order inadmissible.

Keywords

AI generated
extraordinary review administrative order construction suspension statutory time limit inadmissible proceedings legal validity procedural bar

Cited Legislation

AI generated
Art. 50 ust. 1 i 4 ustawy z dnia 7 lipca 1994 r. Prawo budowlane
art. 105 § 1 KPA
art. 22 ust. 1 pkt 1 i ust. 2 pkt 1 ustawy z dnia 11 maja 1995 r. o Naczelnym Sądzie Administracyjnym
art. 50 ust. 1 pkt 3 Prawa budowlanego
art. 77 § 1, art. 80 i art. 107 § 3 KPA
art. 10 ustawy z dnia 1 marca 1996 r. o zmianie Kodeksu postępowania cywilnego
art. 98 ustawy z dnia 29 sierpnia 1997 r. o komornikach sądowych i egzekucji
art. 39312 KPC