Legislator Case Law & Legislation
III RN 40/97 AI generated

Supreme Court allows partial termination of a single perpetual use contract for specific plots used contrary to terms.

Case Number III RN 40/97
Court / Authority
Jurisdiction Poland (PL)
Decision Date
Outcome Allowed / Granted

Legislator summary

AI generated

The Supreme Court upheld the extraordinary review by the Chief Administrative Court regarding the partial termination of a perpetual use agreement. The City Council sought to terminate the contract only for plots used inconsistently with the agreement, while the Housing Cooperative argued the entire contract must be dissolved. The Court ruled that the technical form of the contract does not legally prevent partial termination when specific plots are misused.

Legislator headnote

AI generated

Art. 240 Kodeksu cywilnego; Art. 26 ust. 2 ustawy o gospodarce gruntami: The administrative authority may issue a decision to partially terminate a perpetual use contract for specific plots if the user exploits them contrary to the agreed purpose, regardless of whether the contract covers multiple plots as a single agreement.

Keywords

AI generated
perpetual use contract partial termination extraordinary review land management contrary to terms administrative decision single agreement multiple plots

Cited Legislation

AI generated
Art. 240 Kodeksu cywilnego
Art. 26 ust. 2 ustawy z dnia 29 kwietnia 1985 r. o gospodarce gruntami i wywłaszczaniu nieruchomości