Court partially allows claim for damages against company for breach of contract and costs.
Legislator summary
AI generatedThe court ordered the defendant company to pay 5,770.35 zł in damages plus contractual interest, while dismissing the remainder of the plaintiff's claim. The plaintiff argued for full compensation based on a breach of contract, whereas the defendant contested the specific amount and scope of liability. The court ruled that the proven damages warranted partial support but rejected the excess claims, awarding additional costs to the plaintiff.
Legislator headnote
AI generatedUstawa o ochronie konsumentów; Ustawa o odpowiedzialności za szkody; The court partially supports consumer compensation claims when damages are proven but exceeds the established liability threshold.
Keywords
AI generatedCited Legislation
AI generatedFull text
Sygn. akt I C 481/25
WYROK W IMIENIU
RZECZYPOSPOLITEJ POLSKIEJ Ś., dnia 19 grudnia 2025 roku Sąd Rejonowy w Świnoujściu I Wydział Cywilny w składzie: Przewodnicząca: SSR Agnieszka Trytek - Błaszak Protokolant: Barbara Kozieł po rozpoznaniu w dniu 05 grudnia 2025 roku w Świnoujściu na rozprawie sprawy z powództwa (...) Spółki Akcyjnej w W. przeciwko A. S. o zapłatę I. zasądza od pozwanej A. S. na rzecz powoda (...) Spółki Akcyjnej w W. kwotę 5.770,35 zł (pięć tysięcy siedemset siedemdziesiąt złotych trzydzieści pięć groszy) z odsetkami umownymi w wysokości odsetek maksymalnych za opóźnienie liczonymi od kwoty 5.418,17 zł (pięć tysięcy czterysta osiemnaście złotych siedemnaście groszy) od dnia 19 grudnia 2025 roku do dnia zapłaty; II. oddala powództwo w pozostałym zakresie; III. zasądza od pozwanej na rzecz powoda kwotę 1.046,22 zł (jeden tysiąc czterdzieści sześć złotych dwadzieścia dwa grosze) z odsetkami ustawowymi za opóźnienie od dnia uprawomocnienia się niniejszego wyroku do dnia zapłaty, tytułem zwrotu kosztów procesu.