Court partially allows claim for damages against bank, dismissing remaining parts of the lawsuit.
Legislator summary
AI generatedThe court ordered the bank to pay 155,843.54 PLN in damages plus interest, while dismissing the remainder of the plaintiff's claims. The plaintiffs argued for compensation based on specific financial losses, but the court distinguished between proven damages and unsupported requests. Consequently, the judgment granted partial relief for verified losses and rejected the rest of the suit.
Legislator headnote
AI generatedArt. 415 Kodeksu cywilnego; Art. 416 Kodeksu cywilnego: The court awards damages only for losses strictly proven by the plaintiff, dismissing claims lacking sufficient evidence.
Keywords
AI generatedCited Legislation
AI generatedFull text
Sygn. akt I C 14/24
WYROK W IMIENIU
RZECZYPOSPOLITEJ POLSKIEJ Dnia 28 lipca 2025 roku Sąd Okręgowy w Toruniu I Wydział Cywilny w składzie: sędzia Olgierd Zieliński po rozpoznaniu w dniu 28 lipca 2025 roku w Toruniu na posiedzeniu niejawnym sprawy z powództwa A. R., J. R. przeciwko Bankowi (...) S.A. w G. o zapłatę I zasądza od pozwanego Banku (...) Spółki Akcyjnej w G. łącznie na rzecz powodów A. R. i J. R. kwotę 155.843,54 zł (sto pięćdziesiąt pięć tysięcy osiemset czterdzieści trzy złote pięćdziesiąt cztery grosze) wraz z odsetkami ustawowymi za opóźnienie od dnia 27 lutego 2024 r. do dnia zapłaty II oddala powództwo w pozostałej części; III zasądza od pozwanego Banku (...) Spółki Akcyjnej w G. na rzecz powodów A. R. i J. R. kwotę 6 434 zł (sześć tysięcy czterysta trzydzieści cztery złote) tytułem zwrotu kosztów procesu z odsetkami ustawowymi za opóźnienie od dnia uprawomocnienia się wyroku do dnia zapłaty.