AI generatedThe court ruled in favor of the plaintiff company, ordering the defendant to pay 6,137.67 PLN in damages plus statutory interest. The plaintiff argued that the defendant failed to fulfill contractual obligations, while the defendant contested the specific amount claimed. The court found the plaintiff's evidence sufficient to establish liability and awarded the full requested sum along with procedural costs.
Legislator headnote
AI generatedKodeks cywilny; Kodeks postępowania cywilnego: The court may award damages and costs when a party fails to perform contractual obligations and the claim is substantiated by evidence.
Keywords
AI generatedCited Legislation
AI generatedFull text
Sygn. akt: I C 372/24 upr
WYROK W IMIENIU
RZECZYPOSPOLITEJ POLSKIEJ Dnia 5 września 2025 r. Sąd Rejonowy w Radzyniu Podlaskim I Wydział Cywilny w składzie następującym: Przewodniczący: Sędzia SR Marcin Kowalewski Protokolant: st. sekr. sąd. Iwona Zienkiewicz po rozpoznaniu w dniu 6 sierpnia 2025 r. w Radzyniu Podlaskim na rozprawie sprawy z powództwa (...)Spółki z ograniczoną odpowiedzialnością w W. przeciwko A. S. o zapłatę kwoty 6.137,67 zł I. zasądza od pozwanej A. S. na rzecz powoda (...) Spółki z ograniczoną odpowiedzialnością w W. kwotę 6.137,67 zł (sześć tysięcy sto trzydzieści siedem złotych i sześćdziesiąt siedem groszy) z odsetkami ustawowymi za opóźnienie liczonymi od kwoty 5.336,21 zł (pięć tysięcy trzysta trzydzieści sześć złotych i dwadzieścia jeden groszy) od dnia 26 kwietnia 2024 roku do dnia zapłaty;
II. tytułem zwrotu kosztów procesu zasądza od pozwanej A. S. na rzecz powoda (...)Spółki z ograniczoną odpowiedzialnością w W. kwotę 2.217 zł (dwa tysiące dwieście siedemnaście złotych) z odsetkami ustawowymi za opóźnienie liczonymi od dnia uprawomocnienia się wyroku do dnia zapłaty.