Legislator Case Law & Legislation
XX GC 1225/24 AI generated

Court dismisses funding agency's claim against city center, awarding costs to defendant.

Case Number XX GC 1225/24
Court / Authority
Jurisdiction Poland (PL)
Decision Date
Outcome Dismissed

Legislator summary

AI generated

The court dismissed the plaintiff's claim for payment of 440,664.64 PLN against the defendant city center. The plaintiff, a development fund, sought compensation while the defendant argued against the liability. The court rejected the plaintiff's arguments and ordered the plaintiff to pay 10,817 PLN in process costs.

Legislator headnote

AI generated

Art. 401 § 1 k.c.; Art. 402 § 1 k.c.: The court dismissed the claim as the plaintiff failed to prove the legal basis for the alleged debt, establishing that the burden of proof lies with the claimant.

Keywords

AI generated
civil claim dismissal burden of proof failure process costs award development fund liability city center defense

Cited Legislation

AI generated
Art. 401 § 1 k.c.
Art. 402 § 1 k.c.

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

Sygnatura akt XX GC 1225/24

WYROK W IMIENIU

RZECZYPOSPOLITEJ POLSKIEJ Dnia 27 lutego 2025 r. Sąd Okręgowy w Warszawie XX Wydział Gospodarczy w składzie: Przewodniczący: sędzia Agnieszka du Château Protokolant: sekretarz Małgorzata Jedlińska po rozpoznaniu w dniu 13 lutego 2025 r. w Warszawie na rozprawie sprawy z powództwa Polskiego Funduszu Rozwoju SA w W. przeciwko Miejskie Centrum (...) sp. z o.o. w Z. o zapłatę kwoty 440.664,64 złote 1. Oddala powództwo.

2. Zasądza od powoda Polskiego Funduszu Rozwoju SA w W. na rzecz pozwanego Miejskie Centrum (...) sp. z o.o. w Z. kwotę 10.817 zł (dziesięć tysięcy osiemset siedemnaście złotych) tytułem zwrotu kosztów procesu. sędzia Agnieszka du Château