AI generatedThe court partially dismissed the cooperative housing society's claim, ordering the tenant to pay the principal rent amount plus statutory interest while dismissing the remainder. The tenant argued against the full liability, but the court found the debt valid based on the lease terms. Consequently, the judgment awarded the specific rent sum and process costs to the cooperative.
Legislator headnote
AI generatedCivil Code provisions on lease contracts; The court holds that a landlord may recover unpaid rent and process costs when the tenant fails to fulfill contractual obligations without valid defense.
Keywords
AI generatedCited Legislation
AI generatedFull text
Sygn. akt I C 549/17
WYROK W IMIENIU
RZECZYPOSPOLITEJ POLSKIEJ Dnia 8 września 2017 r. Sąd Rejonowy dla W. M.w W., Wydział I Cywilny w następującym składzie: Przewodniczący: SSR Robert Bełczącki Protokolant: Martyna Arcon po rozpoznaniu w dniu 25 sierpnia 2017 r. w W. na rozprawie sprawy z powództwa Spółdzielni Mieszkaniowej (...) w W. przeciwko Z. G. (Z. G.) o zapłatę kwoty 23.099,35 zł wraz z odsetkami orzeka: I. zasądza od Z. G. na rzecz Spółdzielni Mieszkaniowej (...) w W. kwotę 20.239,48 zł wraz z odsetkami ustawowymi za opóźnienie od dnia 29 czerwca 2016 r. do dnia zapłaty, a w pozostałym zakresie powództwo oddala; II. zasądza od Z. G. na rzecz Spółdzielni Mieszkaniowej (...) w W. kwotę 4.772 zł tytułem kosztów procesu. SSR Robert Bełczącki