Court partially allows claim for damages against company for breach of contract and non-performance.
Legislator summary
AI generatedThe court ordered the defendant company to pay the plaintiff 164,605.25 PLN plus statutory interest, while dismissing the remainder of the claim. The plaintiff alleged a breach of contract and failure to perform obligations, arguing for full compensation. The court found partial liability based on the proven damages but rejected other requests due to lack of evidence or legal basis.
Legislator headnote
AI generatedUstawa o odpowiedzialności cywilnej; Kodeks cywilny: The court partially supports a civil claim for damages when the breach is proven but the scope of liability is limited by the evidence presented.
Keywords
AI generatedCited Legislation
AI generatedFull text
Sygn. akt XX GC 29/12
WYROK W IMIENIU
RZECZYPOSPOLITEJ POLSKIEJ Dnia 4 października 2013 r. Sąd Okręgowy w Warszawie XX Wydział Gospodarczy w składzie: Przewodniczący: SSR del. Arkadiusz Zagrobelny Protokolant: Agnieszka Kacprzak po rozpoznaniu w dniu 26 września 2013 r. w Warszawie na rozprawie sprawy z powództwa K. M. przeciwko (...) sp. z o.o. w W. o zapłatę orzeka:
1. zasądza od (...) sp. z o.o. w W. na rzecz K. M. kwotę 164.605,25 zł (sto sześćdziesiąt cztery tysiące sześćset pięć złotych 25/100) wraz z ustawowymi odsetkami od dnia 11 lutego 2009r do dnia zapłaty;
2. oddala powództwo w pozostałym zakresie. SSR del. Arkadiusz Zagrobelny