Court partially allowed construction company's claim for unpaid construction costs and process costs against a municipality.
Legislator summary
AI generatedThe court ordered the municipality to pay the construction company 814,461.03 PLN for unpaid construction costs plus statutory interest, while dismissing the remainder of the claim. The plaintiff argued that the defendant failed to pay agreed sums for completed work, whereas the defendant contended the scope of services was disputed. The court ruled in favor of the plaintiff regarding the specific construction debt but rejected other requests, awarding process costs to the winner.
Legislator headnote
AI generatedArt. 405 ust. 1 k.c.; Art. 410 k.c.: A court must adjudicate on the specific claim for construction costs if proven, but dismiss unrelated portions of the plaintiff's request if unsupported by evidence.
Keywords
AI generatedCited Legislation
AI generatedFull text
Sygn. akt VI GC 136/20
WYROK W IMIENIU
RZECZYPOSPOLITEJ POLSKIEJ Dnia 3 listopada 2022 roku Sąd Okręgowy w Toruniu VI Wydział Gospodarczy w składzie: Przewodniczący: SSO Stella Czołgowska po rozpoznaniu w dniu 3 listopada 2022 roku w Toruniu na posiedzeniu niejawnym sprawy z powództwa (...) S.A. w T. (poprzednio Przedsiębiorstwo Budownictwa (...) S.A. w T.) przeciwko Gminie M. W. o zapłatę 1. zasądza od pozwanego Gminy M. W. na rzecz powoda (...) S. A. w T. (poprzednio Przedsiębiorstwo Budownictwa (...) S.A. w T.) kwotę 814.461,03 zł (osiemset czternaście tysięcy czterysta sześćdziesiąt jeden złotych trzy grosze) z odsetkami ustawowymi za opóźnienie od dnia 21 lutego 2019 r. do dnia zapłaty, 2. oddala powództwo w pozostałym zakresie, 3. zasądza od pozwanego na rzecz powoda kwotę 52.899,12 zł (pięćdziesiąt dwa tysiące osiemset dziewięćdziesiąt dziewięć złotych dwanaście groszy) tytułem zwrotu kosztów procesu. SSO Stella Czołgowska