Court orders payment of damages and costs to plaintiff company against defendant company for breach of contract.
Legislator summary
AI generatedThe court ruled in favor of the plaintiff company, ordering the defendant to pay 1,390.12 zł in damages plus interest and 740 zł in procedural costs. The plaintiff argued that the defendant failed to fulfill contractual obligations, while the defendant contested the specific amount claimed. The court found the plaintiff's evidence sufficient to establish liability and granted the requested monetary relief.
Legislator headnote
AI generatedUstawa o Kodeksie cywilnym; Kodeks postępowania cywilnego: When a party fails to perform contractual obligations, the court may award damages and costs to the aggrieved party upon proof of loss.
Keywords
AI generatedCited Legislation
AI generatedFull text
Sygn. akt IV GC upr 110/21
WYROK W IMIENIU
RZECZYPOSPOLITEJ POLSKIEJ Dnia 8 kwietnia 2022 roku Sąd Rejonowy dla Wrocławia-Fabrycznej, Wydział IV Gospodarczy w składzie: Przewodniczący: SSR Filip Wesołowski Protokolant: Nicola Kubik po rozpoznaniu w dniu 11 marca 2022 roku we Wrocławiu na rozprawie sprawy z powództwa (...) spółki z o.o. w D. przeciwko (...) spółce z o.o. w O. o zapłatę I. zasądza od strony pozwanej na rzecz strony powodowej kwotę 1390,12 zł (jeden tysiąc trzysta dziewięćdziesiąt złotych i dwanaście groszy) wraz z ustawowymi odsetkami za opóźnienie w transakcjach handlowych od dnia 19 kwietnia 2019 roku do dnia zapłaty; II. zasądza od strony pozwanej na rzecz strony powodowej kwotę 740 zł kosztów procesu. Z/ 1. odnotować, 2. kal. 7 dni.