Legislator Case Law & Legislation
I C 753/20 AI generated

Contractor's breach of contract not excused by epidemic due to lack of causation proof.

Case Number I C 753/20
Court / Authority
Jurisdiction Poland (PL)
Decision Date
Outcome Dismissed

Legislator summary

AI generated

The court dismissed the contractor's claim that the epidemic constituted a force majeure preventing contract performance. The plaintiff argued the epidemic caused the breach, but the defendant failed to prove a direct causal link between the pandemic and the defective execution. Consequently, the court ruled that the epidemic did not legally excuse the contractual obligation.

Legislator headnote

AI generated

Civil Code provisions on force majeure; A state of emergency or epidemic does not constitute force majeure unless the party proves it directly prevented performance.

Keywords

AI generated
force majeure epidemic contractual breach causation civil liability

Cited Legislation

AI generated
Civil Code provisions on force majeure

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

nie sposób uznać, że stan epidemiczny stanowił siłę wyższą, uniemożliwiającą pozwanemu prawidłową realizację jego zobowiązania. Pozwany nie wykazał tego zarzuty, ani związku przyczynowego pomiędzy stanem epidemicznym a wadliwością wykonania przedmiotu umowy.