Contract termination for delay requires Art. 644 k.c. if no completion deadline was set under Art. 635 k.c.
Legislator summary
AI generatedThe court dismissed the plaintiff's claim for contract termination based on Article 635 of the Civil Code due to the absence of a fixed completion deadline. The defendant argued that without a specific time limit, the plaintiff could not rely on Article 635 to declare the contract void. The court held that Article 635 cannot serve as the legal basis for termination in this scenario, requiring instead the application of Article 644 k.c. for such a declaration.
Legislator headnote
AI generatedArt. 635 k.c.; Art. 644 k.c.: If no completion deadline was agreed upon, Article 635 of the Civil Code cannot be the legal basis for a declaration of termination; only Article 644 k.c. may serve as the foundation for such a declaration.
Keywords
AI generatedCited Legislation
AI generatedFull text
Jeżeli nie został pomiędzy stronami ustalony termin ukończenia dzieła, tak aby zamawiający mógł przewidzieć, że wykonawca nie ukończy dzieła w czasie umówionym, art.635 k.c. nie może stanowić podstawy prawnej do złożenia oświadczenia woli o odstąpieniu od umowy, a podstawą takiego oświadczenia może być wyłącznie art. 644 k.c.