Legislator Case Law & Legislation
I C 260/19 AI generated

Civil court dismisses plaintiff's claim against city mayor and city for payment of legal costs.

Case Number I C 260/19
Court / Authority
Jurisdiction Poland (PL)
Decision Date
Outcome Dismissed

Legislator summary

AI generated

The civil court rejected the plaintiff's lawsuit against the mayor and the city, ruling that the plaintiff must bear the legal costs. The plaintiff sought payment from the city officials, but the court found no basis for the claim against the public entities. Consequently, the court ordered the plaintiff to pay 10,800 PLN in legal fees to the city.

Legislator headnote

AI generated

Ustawa o postępowaniu cywilnym; Art. 101 § 1 k.p.c.: The court may reject a claim against a public entity if the claim lacks legal basis, thereby shifting the burden of legal costs to the unsuccessful plaintiff.

Keywords

AI generated
civil procedure public entity liability legal costs claim rejection procedural dismissal

Cited Legislation

AI generated
Ustawa o postępowaniu cywilnym
Art. 101 § 1 k.p.c.

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

Sygn. akt I C 260/19

WYROK W IMIENIU

RZECZYPOSPOLITEJ POLSKIEJ Dnia 21 czerwca 2021r. Sąd Okręgowy w Łodzi I Wydział Cywilny w składzie następującym: Przewodniczący : S.S.O. Marzena Kluba Protokolant : st.sekr. sąd. Beata Barańska po rozpoznaniu w dniu 7 czerwca 2021r w Łodzi na rozprawie sprawy z powództwa B. Z. przeciwko Prezydentowi Miasta S. i Miastu S. o zapłatę 1. odrzuca pozew przeciwko Prezydentowi Miasta S.

2. oddala powództwo w stosunku do Miasta S.;

3. zasądza od powoda na rzecz pozwanego Miasta S. kwotę 10.800,- (dziesięć tysięcy osiemset) złotych tytułem zwrotu kosztów zastępstwa procesowego.