AI generatedThe court ruled in favor of the plaintiff, ordering the defendant to pay damages totaling 7,053.32 PLN plus statutory interest and 3,121.84 PLN in procedural costs. The plaintiff argued for compensation due to the defendant's failure to fulfill contractual obligations, while the defendant contested the specific amounts claimed. The court upheld the claim by validating the evidence presented and calculating the debt based on the proven breach.
Legislator headnote
AI generatedCivil Code provisions on breach of contract; the court established that a party failing to perform contractual duties must compensate the other for resulting losses and bear procedural expenses.
Keywords
AI generatedFull text
Sygn. akt: I C 349/18
WYROK W IMIENIU
RZECZYPOSPOLITEJ POLSKIEJ Dnia 20 grudnia 2019 r. Sąd Rejonowy w Kościerzynie I Wydział Cywilny w składzie następującym: Przewodniczący: Sędzia Karolina Kozieł Protokolant: sekretarz sądowy Magdalena Zinka po rozpoznaniu w dniu 6 grudnia 2019 r. w Kościerzynie na rozprawie sprawy z powództwa S. W. przeciwko I. P. o zap łatę 1. zasądza od pozwanej na rzecz powódki kwotę 7053,32,- zł (siedem tysięcy pięćdziesiąt trzy 32/100) z odsetkami ustawowymi za opóźnienie liczonymi od kwoty: - 6753,32,- zł od 17.10.2017 r. do dnia zapłaty - 300,- zł od 30.08.2018 r. do dnia zapłaty 2. zasądza od pozwanej na rzecz powódki kwotę 3121,84,- zł (trzy tysiące sto dwadzieścia jeden 84/100) tytułem zwrotu kosztów postępowania w tym koszty zastępstwa procesowego w wysokości 1817,- zł 3. zwraca powódce kwotę kwotę 48,16,- zł tytułem niewykorzystanej części zaliczki uiszczonej przez nią na poczet wynagrodzenia biegłego sądowego.