Court dismisses request to establish contract invalidity due to missing loan regulations preventing full assessment.
Legislator summary
AI generatedThe court dismissed the plaintiff's request to establish the invalidity of a loan contract because the plaintiff failed to submit the relevant loan regulations. Without these documents, the court could not reconstruct the full legal relationship or verify the claim's validity. Consequently, the procedural requirement for evidence was not met, leading to the rejection of the motion.
Legislator headnote
AI generatedArt. 357 § 5 k.p.c.; The court cannot assess the validity of a contract if the plaintiff fails to provide necessary regulations required to reconstruct the legal relationship.
Keywords
AI generatedCited Legislation
AI generatedFull text
sygn. XXV C 3644/20 POSTANOWIENIE Dnia 18 listopada 2020 roku Sąd Okręgowy w Warszawie XXV Wydział Cywilny w składzie Przewodniczący: Sędzia (del.) Kamil Gołaszewski po rozpoznaniu 18 listopada 2020 roku na posiedzeniu niejawnym w sprawie z powództwa J. T., A. T. przeciwko (...) SA w W. o ustalenie i zapłatę wniosku powodów o udzielenie zabezpieczenia postanawia: oddalić wniosek. Zasadnicze powody rozstrzygnięcia (art.357§5 kpc) Strona powodowa nie przedłożyła Regulaminu udzielania kredytów i pożyczek hipotecznych dla osób fizycznych w ramach (...) (§26 umowy), co uniemożliwia odtworzenie pełnej treści łączącego strony stosunku prawnego a w konsekwencji dokonania oceny uprawdopodobnienia roszczenia o ustalenie nieważności umowy. (...)