Court dismisses part of housing association's claim for unpaid rent while awarding damages and costs.
Legislator summary
AI generatedThe court dismissed the plaintiff's claim for unpaid rent from 2012 to 2015 but awarded damages and costs for the period in dispute. The housing association argued for full payment of arrears, while the defendant contested the calculation of the debt. The court ruled that the specific period was valid for damages but rejected the main claim for the earlier period.
Legislator headnote
AI generatedArt. 401 k.c.; Art. 402 k.c.: The court may award damages for non-performance of an obligation but may reject the main claim for payment if the underlying debt is not established for the requested period.
Keywords
AI generatedCited Legislation
AI generatedFull text
Sygnatura akt I C 552/18
WYROK W IMIENIU
RZECZYPOSPOLITEJ POLSKIEJ (...), dnia 19 marca 2021 r. Sąd Okręgowy w Łodzi I Wydział Cywilny w następującym składzie: Przewodniczący:SSO Karol Ike-Duninowski Protokolant:st. sekr. sąd. Magdalena Lelewska po rozpoznaniu w dniu 5 marca 2021 r. w Łodzi na rozprawie sprawy z powództwa Wspólnoty Mieszkaniowej Ł. ul. (...) z siedzibą w Ł. przeciwko (...) Spółce Akcyjnej z siedzibą w Ł. o zapłatę 1. zasądza od (...) Spółce Akcyjnej z siedzibą w Ł. na rzecz Wspólnoty Mieszkaniowej Ł. ul. (...) z siedzibą w Ł. kwotę 460.538,48 (czterysta sześćdziesiąt tysięcy pięćset trzydzieści osiem i 48/100) złotych z odsetkami ustawowymi od dnia 21 listopada 2012 r. do dnia 31 grudnia 2015 r. oraz z odsetkami ustawowymi za opóźnienie od dnia 1 stycznia 2016 r. do dnia zapłaty oraz kwotę 10.817 (dziesięć tysięcy osiemset siedemnaście) złotych tytułem zwrotu kosztów procesu;
2. oddala powództwo w pozostałej części.