Legislator Case Law & Legislation
I C 881/18 AI generated

Civil court dismisses plaintiff's claim for payment and costs against defendant in a debt dispute.

Case Number I C 881/18
Court / Authority
Jurisdiction Poland (PL)
Decision Date
Outcome Dismissed

Legislator summary

AI generated

The civil court dismissed the plaintiff's claim for payment and costs against the defendant. The plaintiff sought monetary compensation based on a specific debt, while the defendant contested the validity of the claim. The court ruled against the plaintiff, ordering them to bear all procedural costs.

Legislator headnote

AI generated

Art. 385 ust. 1 k.p.c.; Art. 386 k.p.c.: The court dismisses the plaintiff's claim if the defendant successfully contests the debt and the plaintiff fails to prove the obligation exists.

Keywords

AI generated
civil debt dispute dismissal of claim procedural costs burden of proof plaintiff liability

Cited Legislation

AI generated
Art. 385 ust. 1 k.p.c.
Art. 386 k.p.c.

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

Sygn. akt: I C 881/18 WYROK W IMIENIU RZECZYPOSPOLITEJ POLSKIEJ Dnia 23 grudnia 2020 roku Sąd Rejonowy w Głubczycach I Wydział Cywilny w składzie następującym: Przewodniczący: SSR Krzysztof Chruszczewski Protokolant: sekretarz sądowy Agnieszka Krzysztoń po rozpoznaniu w dniu 9 grudnia 2020 roku sprawy z powództwa M. H. przeciwko H. O. o zapłatę i wydanie 1. oddala powództwo. 2. kosztami postępowania w całości obciąża powoda M. H., pozostawiając referendarzowi sądowemu szczegółowe wyliczenia tych kosztów.