XIII GC 1085/20 AI generated

Contractual penalty claim dismissed when breach was non-monetary debt failure, not contract withdrawal.

Case Number XIII GC 1085/20
Court / Authority
Jurisdiction Poland (PL)
Decision Date
Outcome Dismissed

Legislator summary

AI generated

The court dismissed the plaintiff's claim for a contractual penalty reserved for contract withdrawal. The plaintiff argued that the defendant's failure to pay a monetary debt constituted a valid ground for withdrawing the contract and triggering the penalty. The court ruled that such a failure does not justify contract withdrawal under the relevant provisions, thereby precluding the penalty claim.

Legislator headnote

AI generated

Art. 387 ust. 1 k.c.; Art. 388 k.c.: A contractual penalty reserved for contract withdrawal cannot be claimed if the contract is terminated due to the debtor's failure to perform a monetary obligation.

Keywords

AI generated
contractual penalty contract withdrawal monetary debt breach of contract civil code provisions

Cited Legislation

AI generated
Art. 387 ust. 1 k.c.
Art. 388 k.c.

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

Brak jest podstaw do domagania się zasądzenia kary umownej zastrzeżonej na wypadek odstąpienia od umowy, gdy podstawę odstąpienia stanowiło niewykonanie zobowiązania pieniężnego.