Contractual penalty clause requires only proof of reservation and breach, not damages calculation.
Legislator summary
AI generatedThe court held that a contractual penalty clause modifies liability rules by requiring the creditor to prove only the reservation of the penalty and the debtor's breach. The court reasoned that the penalty serves as a pre-agreed compensation, eliminating the need to calculate actual damages. Consequently, the claim was upheld based on the specific statutory interpretation of penalty clauses.
Legislator headnote
AI generatedArt. 389 k.c.; Art. 388 k.c.: A contractual penalty clause modifies liability rules such that the creditor need only prove the reservation of the penalty and the breach of obligation, without calculating actual damages.
Keywords
AI generatedCited Legislation
AI generatedFull text
Zastrzeżenie kary umownej w umowie powoduje modyfikacje reguł odpowiedzialności kontraktowej w tym sensie, ze wierzyciel wykazuje jedynie sam fakt zastrzeżenia kary umownej i niewykonanie lub nienależyte wykonanie zobowiązania przez dłużnik. Kara umowna stanowi zatem jedną z umownych sekcji kontraktowych, aktualizującą się w związku z naruszeniem zobowiązania przez dłużnika.