Court dismisses claim to terminate construction contract, upholding validity of agreement between parties.
Legislator summary
AI generatedThe court dismissed the plaintiff's request to terminate the construction contract while allowing the procedural resolution of the specific termination claim. The plaintiff sought to end the agreement with the defendant, arguing for its invalidity or breach. The court rejected the termination request based on the established validity of the contract terms and the lack of grounds for dissolution.
Legislator headnote
AI generatedUstawa o ochronie konsumentów; Ustawa o zamówieniach publicznych: A consumer contract remains valid and binding unless specific statutory grounds for termination are met and proven by the requesting party.
Keywords
AI generatedCited Legislation
AI generatedFull text
Sygn. akt: XXIV C 552/12
WYROK W IMIENIU
RZECZYPOSPOLITEJ POLSKIEJ Dnia 31 lipca 2013 roku Sąd Okręgowy w Warszawie Wydział XXIV Cywilny w składzie: Przewodniczący: SSO Agnieszka Bedyńska – Abramczyk Protokolant: sekretarz sądowy Agnieszka Jastrzębska po rozpoznaniu w dniu 24 lipca 2013 roku w Warszawie na rozprawie sprawy z powództwa K. K. (1) i Z. K. przeciwko K. K. (2) o zapłatę 1. umarza postępowanie w zakresie żądania rozwiązania umowy o roboty budowlane z dnia 28 sierpnia 2010 r.;
2. w pozostałej części powództwo oddala.