Contract dispute dismissed; court rejected claims for additional work and contractual penalties due to lack of evidence.
Legislator summary
AI generatedThe court dismissed the plaintiff's claims regarding contractual penalties, delays, and additional work payments. The plaintiff argued for compensation based on unperformed obligations and extra labor, while the defendant contested these by asserting set-off rights and lack of formal notification requirements. The court ruled against the plaintiff because the evidence failed to substantiate the alleged additional work or prove the conditions for imposing contractual penalties.
Legislator headnote
AI generatedCivil Code provisions on contractual liability; the court held that claims for additional work and penalties require strict proof of causation and procedural compliance, which were absent here.
Keywords
AI generatedFull text
"Spór pomiędzy stronami dotyczył zasadności naliczenia kar umownych, przyczyn powstałych opóźnień i ustalenia ciężaru odpowiedzialności za nieterminowość w wykonaniu przedmiotu umowy, zasadności żądania zapłaty za wykonane przez powoda roboty określane jako dodatkowe, ale też zapłaty kwot wynikających z umów Nr (…)i Nr (…)w części, w której nie zostały ona uiszczone wobec złożenia przez pozwanego oświadczenia o potrąceniu, tj. w wysokości dochodzonej pozwem, obowiązku zawiadomienia o wykonywaniu części prac przez podwykonawcę