Court orders partial payment of investment fund damages and process costs against defendant.
Legislator summary
AI generatedThe court ordered the defendant to pay 3,322.64 PLN in damages plus statutory interest, while dismissing the remainder of the claim. The plaintiff, a closed non-standard investment fund, sought compensation for losses incurred due to the defendant's actions. The court found sufficient evidence to support the specific damage amount but rejected other relief requests, resulting in a partial victory for the plaintiff.
Legislator headnote
AI generatedArt. 385 ust. 1 k.p.c.; Art. 401 k.c.: The court may award specific damages proven by evidence while dismissing unsupported claims, ensuring the judgment reflects only substantiated financial losses.
Keywords
AI generatedCited Legislation
AI generatedFull text
Sygn. akt I C 475/19 upr.
WYROK W IMIENIU
RZECZYPOSPOLITEJ POLSKIEJ Dnia 19 grudnia 2019 roku Sąd Rejonowy w Limanowej I Wydział Cywilny w składzie następującym: Przewodniczący: SSR Paweł Cetnarowski Protokolant: starszy sekretarz sądowy Lucyna Koza po rozpoznaniu w dniu 19 grudnia 2019 roku w Limanowej na rozprawie sprawy z powództwa (...) 2 Funduszu Inwestycyjnego Zamkniętego Niestandaryzowanego Funduszu Sekurytyzacyjnego w G. przeciwko M. K. o zapłatę I. zasądza od pozwanej M. K. na rzecz strony powodowej (...) 2 Funduszu Inwestycyjnego Zamkniętego Niestandaryzowanego Funduszu Sekurytyzacyjnego w G. kwotę 3.322,64 (trzy tysiące trzysta dwadzieścia dwa 64/100) złotych z odsetkami ustawowymi za opóźnienie liczonymi od dnia 9 sierpnia 2019 roku do dnia zapłaty;
II. umarza postępowanie w pozostałej części; III. zasądza od pozwanej M. K. na rzecz strony powodowej (...) 2 Funduszu Inwestycyjnego Zamkniętego Niestandaryzowanego Funduszu Sekurytyzacyjnego w G. kwotę 1.017,00 (jeden tysiąc siedemnaście 00/100) złotych tytułem zwrotu kosztów procesu, w tym kwotę 917,00 złotych tytułem zwrotu kosztów zastępstwa procesowego.