I C 2164/18
AI generated
Court dismissed energy supply contract claims, ruling price hikes were normal market risks assumed by the professional plaintiff.
Legislator summary
AI generatedThe court dismissed the plaintiff's claims against multiple public entities seeking to increase energy supply contract rates. The plaintiff argued that rising energy prices were unforeseeable, but the court found such fluctuations to be normal market risks inherent in professional contracting. Consequently, the plaintiff was ordered to pay the defendants' legal costs as the losing party.
Legislator headnote
AI generatedArt. 357 § 1 k.c.; Art. 235 § 1 k.p.c.: Changes in commodity prices resulting from global market fluctuations constitute normal contractual risks that a professional party must anticipate and price into the contract, thereby barring claims for judicial modification or termination.
Keywords
AI generated
contractual risk allocation
energy supply contracts
market price fluctuations
professional party liability
freedom of contract
public procurement disputes
judicial modification of contracts
Cited Legislation
AI generatedArt. 357 § 1 k.c.
Art. 235 § 1 k.p.c.
Art. 98 k.p.c.
§ 2 pkt 6 i 7 Rozporządzenia Ministra Sprawiedliwości z dnia 22 października 2015 roku w sprawie opłat za czynności radców prawnych
art. 235§1 k.p.c
art. 98 k.p.c
Cited Case Law
AI generatedI ACa 633/16
Appeal dismissed; tenant's claim for rent and improvements rejected due to statute of limitations and lease terms.
VIII GC 93/15
Court dismissed contractor's claim for price adjustment due to unforeseen material cost increases under Polish law.
Sąd Okręgowy w Szczecinie
V ACa 409/10
III CSK 119/05
Supreme Court allows hospital's claim against health fund for statutory wage increase costs under Civil Code.
Related Decisions
AI generatedXVII AmE 139/21
Consumer court dismissed appeal against energy regulator's decision to suspend electricity supply due to unpaid bills.
I C 388/18
Civil court dismissed claim to modify public procurement contract price citing budgetary constraints and final performance.
I C 285/19
Court dismissed public tender contract dispute over energy price increase citing contractual risk.
I C 236/19
Powódka Gmina S. wniosła o zasądzenie od pozwanej (...) Sp. z o. o. z siedzibą we W. kwoty 112.612,51 zł wraz z odsetkami ustawowymi za opóźnienie liczonymi od 7 marca 2019 roku do dnia zapłaty oraz kosztów postępowania, w tym kosztów zastępstwa procesowego według norm przepisanych lub według przedłożonego spisu kosztów, w tym 17 zł opłaty skarbowej od pełnomocnictwa.