Court orders bank to pay defendant over 134k PLN plus costs for breach of contract dispute.
Legislator summary
AI generatedThe court ruled in favor of the bank, ordering the defendant to pay 134,855.47 PLN plus statutory interest and 12,160 PLN in procedural costs. The plaintiff successfully argued that the defendant failed to fulfill contractual obligations, leading to a breach of contract. Consequently, the court granted the claim for payment and awarded the costs of the proceedings.
Legislator headnote
AI generatedCivil Code provisions on breach of contract; the court established that a party failing to perform contractual duties must compensate the other for damages and bear procedural costs.
Keywords
AI generatedCited Legislation
AI generatedFull text
Sygn. akt I C 1354/18
WYROK W IMIENIU
RZECZYPOSPOLITEJ POLSKIEJ Dnia 19 czerwca 2019 roku Sąd Okręgowy w Łodzi I Wydział Cywilny w następującym składzie: Przewodniczący: SSO Paweł Barański Protokolant: st. sekr. sąd. Agnieszka Kowalska po rozpoznaniu w dniu 5 czerwca 2019 roku w Łodzi na rozprawie sprawy z powództwa (...) Bank Spółki Akcyjnej z siedzibą w W. przeciwko J. W. o zapłatę zasądza od J. W. na rzecz (...) Bank Spółki Akcyjnej z siedzibą w W. kwotę 134.855,47 zł (sto trzydzieści cztery tysiące osiemset pięćdziesiąt pięć złotych 47/100) wraz z odsetkami ustawowymi za opóźnienie od dnia 29 grudnia 2017 r. do dnia zapłaty oraz kwotę 12.160 zł (dwanaście tysięcy sto sześćdziesiąt złotych) tytułem zwrotu kosztów postępowania.