Contract penalty deemed not excessive if it creates pressure on the debtor to perform obligations properly.
Legislator summary
AI generatedThe court upheld the contract penalty as not excessive, rejecting the claim that it was unreasonably high. The plaintiff argued the penalty was disproportionate to the actual loss, while the defendant contended it served to ensure timely performance. The court ruled that the penalty's purpose is to exert pressure on the debtor, meaning even a high amount relative to general damages does not constitute excessiveness if it aims to compel proper fulfillment of the contract.
Legislator headnote
AI generatedArt. 484 par. 2 kc; A contract penalty is not considered excessive merely because it exceeds the actual loss, as its primary function is to create pressure on the debtor to perform obligations properly.
Keywords
AI generatedCited Legislation
AI generatedFull text
Rażące wygórowanie kary umownej, o którym mowa w art. 484 par 2 kc jako okoliczność uzasadniająca jej miarkowanie kary umownej winna być analizowana jako porównanie rozmiaru poniesionej szkody w wyniku naruszenia zobowiązania w stosunku do wysokości zastrzeżonej kary umownej a kryterium oceny rażącego wygórowania może być także relacja jej wysokości do odszkodowania należnego wierzycielowi na zasadach ogólnych. Sama zaś dysproporcja w tym zakresie nie uzasadnia zarzutu o rażącym wygórowaniu kary umownej, ponieważ celem zastrzeżenia kary umownej jest wywarcie na dłużniku presji, aby wykonał on swoje zobowiązanie w należyty sposób.