Court orders payment of damages and costs against a company for breach of contract claims.

Case Number II C 1437/16
Court / Authority
Jurisdiction Poland (PL)
Decision Date
Outcome Allowed / Granted

Legislator summary

AI generated

The court ruled in favor of the plaintiff, ordering the defendant company to pay damages and process costs. The plaintiff successfully argued that the defendant failed to fulfill contractual obligations, resulting in financial loss. Consequently, the court awarded the specific monetary amounts requested based on the proven breach.

Legislator headnote

AI generated

Civil Code provisions on breach of contract; the court established that a party failing to perform contractual duties must compensate the other for resulting damages and bear litigation costs.

Keywords

AI generated
breach of contract damages award litigation costs civil liability contractual performance

Cited Legislation

AI generated
Civil Code of the Republic of Poland
Civil Procedure Code of the Republic of Poland

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

Sygn. akt II C 1437/16

WYROK W IMIENIU

RZECZYPOSPOLITEJ POLSKIEJ Dnia 15 lutego 2017 roku Sąd Rejonowy dla W. M. w W.II W. C. w składzie następującym: Przewodniczący: SSR Małgorzata Wert Protokolant: sekretarz sądowy Anna Leciak po rozpoznaniu w dniu 6 lutego 2017 roku w W. na rozprawie sprawy z powództwa P. Z. przeciwko V. Ż. Spółka Akcyjna V. G. z siedzibą w W. o zapłatę 1.zasądza od V. Ż. Spółka Akcyjna V. G. z siedzibą w W. na rzecz P. Z. kwotę 5310,56 zł wraz z ustawowymi odsetkami za opóźnienie od dnia 13 stycznia 2016 roku do dnia zapłaty; 2.zasądza od V. Ż.Spółka Akcyjna V. G.z siedzibą w W. na rzecz P. Z. kwotę 3219,86 zł tytułem zwrotu kosztów procesu .