Court dismisses claim to remove power lines, allowing instead a servitude claim under Polish Civil Code.
Legislator summary
AI generatedThe court dismissed the plaintiff's request to remove energy lines from the property, ruling that the utility company could instead seek a transmission servitude. The plaintiff argued this constituted an abuse of rights, while the defendant maintained the servitude option was legally sufficient. The court held that since a servitude is a valid alternative, demanding physical removal does not constitute an abuse of rights under the Civil Code.
Legislator headnote
AI generatedArt. 222 § 2 k.c.; Art. 305 § 1 k.c.; Art. 305 § 2 k.c.: A request to remove energy lines is not an abuse of rights if the utility company has the option to establish a transmission servitude.
Keywords
AI generatedCited Legislation
AI generatedFull text
Nie stanowi nadużycia prawa podmiotowego ( art. 5 k.c.) żądanie usunięcia z nieruchomości linii energetycznej ( art. 222 §2 k.c.), jeśli przedsiębiorca energetyczny ma możliwość żądania ustanowienia na nieruchomości służebności przesyłu ( art. 305 ¹ k.c. i art. 305 ² k.c.).