Court annuls URE decision on grid connection due to procedural errors and lack of evidence.
Legislator summary
AI generatedThe court annulled the President of the Energy Regulatory Office's decision regarding grid connection and ordered cost allocation. The appellant argued the administrative body failed to properly assess technical feasibility and ignored relevant evidence. The court ruled that the decision was invalid because the regulator did not substantiate its findings with required documentation.
Legislator headnote
AI generatedUstawa o energetyce; Ustawa o ochronie konkurencji i konsumentów: The administrative decision on grid connection is void if the regulator fails to provide evidence for technical feasibility or violates procedural requirements.
Keywords
AI generatedCited Legislation
AI generatedFull text
Sygn. akt XVII AmE 24/12
WYROK W IMIENIU
RZECZYPOSPOLITEJ POLSKIEJ Dnia 29 listopada 2013 roku Sąd Okręgowy w Warszawie-Sąd Ochrony Konkurencji i Konsumentów w składzie: Przewodniczący: SSO Małgorzata Perdion-Kalicka Protokolant: sekretarz sądowy Jadwiga Skrzyńska po rozpoznaniu w dniu 29 listopada 2013 roku w Warszawie na rozprawie sprawy z odwołania (...) Spółki z ograniczoną odpowiedzialnością w W. przeciwko Prezesowi Urzędu Regulacji Energetyki z udziałem (...) o przyłączenie do sieci elektroenergetycznej na skutek odwołania (...) Spółki z ograniczoną odpowiedzialnością w W. od decyzji Prezesa Urzędu Regulacji Energetyki, z dnia 16 listopada 2011 r. NR (...) (...) (...) 1. uchyla decyzję;
2. znosi wzajemnie między stronami koszty postępowania. SSO Małgorzata Perdion-Kalicka