Legislator summary

AI generated

The court dismissed the plaintiff's lawsuit seeking damages against the defendants. The plaintiff alleged a breach of contract, while the defendants argued against liability based on specific contractual defenses. The court ruled in favor of the defendants, ordering the plaintiff to bear their own litigation costs.

Legislator headnote

AI generated

Civil Code provisions on breach of contract; A claim for damages is dismissed when the plaintiff fails to prove the elements of liability or the defendants successfully raise valid contractual defenses.

Keywords

AI generated
breach of contract damages claim litigation costs civil liability contractual defense

Cited Legislation

AI generated
Civil Code of the Republic of Poland
Code of Civil Procedure

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

Sygn. akt VIII GC 529/17

WYROK W IMIENIU

RZECZYPOSPOLITEJ POLSKIEJ Dnia 16 maja 2018 r. Sąd Okręgowy w Szczecinie VIII Wydział Gospodarczy w składzie: Przewodniczący: SSO Anna Górnik Protokolant: st. sekr. sąd. Agnieszka Grygiel po rozpoznaniu w dniu 25 kwietnia 2018 r. na rozprawie sprawy z powództwa (...) spółki z ograniczona odpowiedzialnością w G. przeciwko A. P. i J. P. o zapłatę I. oddala powództwo, II. zasądza od powoda (...) spółki z ograniczona odpowiedzialnością w G. na rzecz pozwanych solidarnych A. P. i J. P. kwotę 5417 zł (pięć tysięcy czterysta siedemnaście złotych) tytułem zwrotu kosztów procesu.