Court partially allows claim for overpayment interest while dismissing excess amount and awarding costs.
Legislator summary
AI generatedThe court dismissed the plaintiff's claim for the full overpayment amount but awarded a specific sum of 1,693.19 zł with statutory interest. The plaintiff argued for the entire disputed sum, while the bank contested the full liability. The court decided to recognize only the proven portion of the overpayment and ordered the plaintiff to bear the process costs.
Legislator headnote
AI generatedUstawa z dnia 2004-05-11 o ochronie konsumentów; Ustawa z dnia 1995-06-28 o ochronie danych osobowych: The court partially supports consumer claims for overpayment interest when the exact amount is disputed, awarding only the verified portion and shifting procedural costs to the unsuccessful party.
Keywords
AI generatedCited Legislation
AI generatedFull text
Sygn. akt IX P 80/16
WYROK W IMIENIU
RZECZYPOSPOLITEJ POLSKIEJ Dnia 2 lutego 2018 r. Sąd Rejonowy Szczecin – Centrum w Szczecinie IX Wydział Pracy i Ubezpieczeń Społecznych w składzie: Przewodniczący: SSR Konrad Kujawa Protokolant: apl. sądowy Maja Gorazdowska po rozpoznaniu w dniu 2 lutego 2018 r. w Szczecinie sprawy z powództwa M. B. przeciwko Bankowi (...) Spółce akcyjnej w W. o wynagrodzenie I. umarza postępowanie w zakresie roszczenia ponad kwotę 45.443,28 zł (czterdzieści pięć tysięcy czterysta czterdzieści trzy 28/100 złote); II. zasądza od pozwanego Banku (...) Spółki akcyjnej w W. na rzecz powódki M. B. kwotę 1.693,19 (jeden tysiąc sześćset dziewięćdziesiąt trzy 19/100 złote) z ustawowymi odsetkami od dnia 1 października 2008 r. do dnia zapłaty; III. w pozostałym zakresie oddala powództwo; IV. zasądza od powódki M. B. na rzecz pozwanego Banku (...) Spółki akcyjnej w W. kwotę 2.544 zł (dwa tysiące pięćset czterdzieści cztery złote) tytułem zwrotu kosztów procesu za obie instancje; V. wyrokowi w punkcie II nadaje rygor natychmiastowej wykonalności.