Court upheld partial payment order against company for debt and costs in commercial dispute.
Legislator summary
AI generatedThe court upheld the mandatory payment order issued on September 21, 2012, confirming the defendant's liability for a specific debt amount. The plaintiff, a limited partnership company, sought payment from the defendant, while the defendant contested the full validity of the claim. The court ruled in favor of the plaintiff regarding the principal sum and associated costs, rejecting the defendant's arguments to the extent they failed to prove non-liability.
Legislator headnote
AI generatedArt. 401 k.c.; Art. 402 k.c.: A court may uphold a partial mandatory payment order when the defendant fails to rebut the evidence establishing the debt, thereby confirming liability for the proven amount and procedural costs.
Keywords
AI generatedCited Legislation
AI generatedFull text
Sygn. akt XX GC 1085/12
WYROK W IMIENIU
RZECZYPOSPOLITEJ POLSKIEJ Dnia 7 stycznia 2014 r. Sąd Okręgowy w Warszawie XX Wydział Gospodarczy w składzie: Przewodniczący: SSO Agnieszka Baran Protokolant: Hanna Nowicka po rozpoznaniu w dniu 7 stycznia 2014 r. w Warszawie na rozprawie sprawy z powództwa Grupa (...) Sp. z o.o. Spółka komandytowa w W. przeciwko M. W. o zapłatę orzeka:
1. utrzymuje nakaz zapłaty w postępowaniu nakazowym z dnia 21 września 2012 roku (Sygn. akt: XX GNc 869/12) w części, tj. co do kwoty 53 316,94 zł (pięćdziesiąt trzy tysiące trzysta szesnaście 94/100 złotych) wraz z ustawowymi odsetkami liczonymi od kwoty 173 316,94 zł (sto siedemdziesiąt trzy tysiące trzysta szesnaście 94/100 złotych) od dnia 21 sierpnia 2012 roku do dnia zapłaty, 2. utrzymuje w mocy orzeczenie o kosztach procesu zawarte w nakazie zapłaty z dnia 21 września 2012 roku (sygn. akt: XX GNc 869/12). SSO Agnieszka Baran