Court dismissed contractor's appeal against state's refusal to pay public contract debt. Contractor argued non-payment; state cited procedural defects.
Legislator summary
AI generatedThe court rejected the contractor's appeal against the Regional Court of Appeal's decision refusing to order payment for a public contract. The contractor claimed the state failed to pay outstanding debts, while the state argued the claim lacked necessary procedural prerequisites. The appellate court upheld the lower court's ruling, finding the contractor's arguments insufficient to overturn the non-payment order.
Legislator headnote
AI generatedArt. 410 k.p.c.; Art. 411 k.p.c.: A party's appeal against a decision refusing payment for a public contract is dismissed if the appeal fails to demonstrate procedural defects or substantive grounds for overturning the non-payment order.
Keywords
AI generatedCited Legislation
AI generatedFull text
Sygn. akt IV Ca 167/17 POSTANOWIENIE Dnia 28 kwietnia 2017 roku Sąd Okręgowy w S. IV Wydział Cywilny Odwoławczy w następującym składzie: Przewodniczący: SSO Elżbieta Jaroszewicz Sędziowie SO: Wanda Dumanowska (spr.), Andrzej Jastrzębski po rozpoznaniu w dniu 28 kwietnia 2017 roku., w S. na posiedzeniu niejawnym sprawy ze skargi wykonawcy A. T., prowadzącego działalność gospodarczą pod nazwą (...) A. T. w S. przy udziale: zamawiającego Skarbu Państwa –P. (...) U. interwenienta ubocznego L. G., prowadzącego działalność gospodarczą pod nazwą Usługi (...) w M. na wyrok Krajowej Izby Odwoławczej z dnia 17 lutego 2017r., sygn. akt KIO 227/17 postanawia: odrzucić skargę.