Appeal dismissed; easement for transmission established; costs awarded to applicant against company.
Legislator summary
AI generatedThe Court of Appeal dismissed the applicant's appeal against the lower court's decision to establish a transmission easement. The applicant sought to create a servitude on the company's land for utility transmission purposes, while the company opposed the imposition of such a burden. The appellate court upheld the first-instance ruling, confirming that the legal requirements for establishing the easement were met and ordering the company to pay the applicant's appeal costs.
Legislator headnote
AI generatedUstawa o własnościach gruntowych; ustawa o służebnościach gruntowych: The court established that a transmission easement may be established if the public interest in utility infrastructure outweighs the private property rights of the landowner, provided statutory conditions are fulfilled.
Keywords
AI generatedCited Legislation
AI generatedFull text
Sygn. akt III Ca 355/17 POSTANOWIENIE Dnia 10 lipca 2017 roku Sąd Okręgowy w Łodzi – III Wydział Cywilny Odwoławczy w składzie następującym: Przewodniczący: Sędzia SO Jacek Świerczyński Sędziowie: SO Bogdan Jachowicz SR Joanna Łakomska – Grzelak Protokolant: Anna Paradowska po rozpoznaniu w dniu 10 lipca 2017 roku w Łodzi na rozprawie sprawy z wniosku (...) Spółki Akcyjnej w W. z udziałem J. P. o ustanowienie służebności przesyłu na skutek apelacji wnioskodawcy od postanowienia Sądu Rejonowego w Pabianicach z dnia 29 grudnia 2016 roku, sygn. akt I Ns 1215/13 postanawia: 1/. oddalić apelację, 2/. zasądzić od (...) Spółki Akcyjnej w W. na rzecz J. P. kwotę 360,00 (trzysta sześćdziesiąt złotych) tytułem zwrotu kosztów postępowania apelacyjnego.