The civil court in Olsztyn dismissed the plaintiff's claim for payment against the defendant. The plaintiff alleged a debt arising from a specific transaction, but failed to provide sufficient evidence of the contract or performance. Consequently, the court ruled that the plaintiff bore the burden of proof which they could not meet.

Legislator headnote

AI generated

Civil Code provisions on burden of proof; the plaintiff must substantiate the existence of a debt obligation with concrete evidence, otherwise the claim is dismissed.

Keywords

AI generated
burden of proof civil claim payment dispute lack of evidence contractual obligation

Cited Legislation

AI generated
Civil Code of the Republic of Poland

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

Sygn. akt: X C 1011/17 WYROK ZAOCZNY W IMIENIU RZECZYPOSPOLITEJ POLSKIEJ Dnia 13 lipca 2017 r. Sąd Rejonowy w Olsztynie X Wydział Cywilny w składzie następującym: Przewodniczący: SSR Wojciech Krawczyk Protokolant: st. sekr. sądowy Lidia Kuzia po rozpoznaniu w dniu 13 lipca 2017 r. w Olsztynie sprawy z powództwa (...) S.A. w B. przeciwko C. T. o zapłatę 1.oddala powództwo. 2. kosztami postępowania obciąża powoda. z./ 1. (...) 2. (...) 3.(...) (...)