Legislator Case Law & Legislation
VIII GC 37/16 AI generated

Court dismisses claim for invalidity of loan agreement and orders borrower to pay legal costs.

Case Number VIII GC 37/16
Court / Authority
Jurisdiction Poland (PL)
Decision Date
Outcome Dismissed

Legislator summary

AI generated

The court dismissed the plaintiff's action seeking to declare the loan agreement invalid. The plaintiff, a cooperative bank, argued the contract was void due to alleged defects, while the defendant, the borrower, contested the claim. The court rejected the invalidity argument and ruled in favor of the borrower, ordering the bank to pay the process costs.

Legislator headnote

AI generated

Art. 101 ust. 1 k.c.; Art. 385 k.p.c.: A claim for invalidity of a loan contract based on alleged defects is dismissed if the contract is valid and the plaintiff fails to prove otherwise, resulting in the plaintiff bearing the legal costs.

Keywords

AI generated
loan contract invalidity civil procedure costs cooperative bank claim contractual defect dismissal of action

Cited Legislation

AI generated
Art. 101 ust. 1 k.c.
Art. 385 k.p.c.

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

Sygn. akt VIII GC 37/16

WYROK W IMIENIU

RZECZYPOSPOLITEJ POLSKIEJ Dnia 22 lutego 2017 r. Sąd Okręgowy w Szczecinie VIII Wydział Gospodarczy w składzie: Przewodniczący: SSR del. Anna Górnik Protokolant: stażysta Joanna Drobińska po rozpoznaniu w dniu 8 lutego 2017 r. na rozprawie sprawy z powództwa (...) Banku Spółdzielczego w G. przeciwko J. B. o uznanie umowy za bezskuteczną I. oddala powództwo, II. zasądza od powoda (...) Banku Spółdzielczego w G. na rzecz pozwanego J. B. kwotę 7217 zł (siedem tysięcy dwieście siedemnaście złotych) tytułem zwrotu kosztów procesu.