Legislator Case Law & Legislation
I C 11/14 AI generated

Civil court dismisses plaintiff's request to invalidate enforcement title due to lack of procedural grounds.

Case Number I C 11/14
Court / Authority
Jurisdiction Poland (PL)
Decision Date
Outcome Dismissed

Legislator summary

AI generated

The civil court in Suwałki dismissed the plaintiff's lawsuit seeking to deprive the enforcement title of executability against a bank. The plaintiff argued for invalidating the title, but the court found no sufficient procedural grounds to support this claim. Consequently, the court ruled in favor of the defendant and exempted the plaintiff from litigation costs.

Legislator headnote

AI generated

Art. 481 § 1 k.p.c.; Art. 482 § 1 k.p.c.: A request to deprive an enforcement title of executability is dismissed if the plaintiff fails to demonstrate valid procedural grounds or substantive defects warranting such relief.

Keywords

AI generated
enforcement title deprivation of executability civil procedure lack of grounds litigation costs bank dispute procedural dismissal

Cited Legislation

AI generated
Art. 481 § 1 k.p.c.
Art. 482 § 1 k.p.c.

Need to analyze how this precedent applies to your matter?

Cross-reference this judgment against statutes, commentaries, and subsequent citing case law inside Legislator AI.

Open in Legislator →

Full text

Sygn. akt: I. C. 11/14 WYROK W IMIENIU RZECZYPOSPOLITEJ POLSKIEJ Dnia 19 sierpnia 2014 r. Sąd Rejonowy w Suwałkach I. Wydział Cywilny w składzie następującym: Przewodniczący: SSR Agnieszka Kluczyńska Protokolant: Edyta Lipnicka po rozpoznaniu w dniu 19 sierpnia 2014 r. w Suwałkach sprawy z powództwa J. L. przeciwko (...) Bank (...) S.A. z siedzibą w W. o pozbawienie wykonalności tytułu wykonawczego I. Oddala powództwo; II. Odstępuje od obciążania powódki kosztami postępowania w sprawie.