Court extends interest calculation deadline from October 2012 to October 2013 in debt appeal. Verdict: allowed.
Legislator summary
AI generatedThe appellate court modified the lower court's judgment to extend the start date of interest calculations on overdue installments from October 26, 2012, to October 26, 2013. The plaintiff argued for the earlier date, while the defendant contended that the interest period should begin later based on specific contractual terms. The court ruled in favor of the defendant, establishing that the interest period commences only after the specified later date.
Legislator headnote
AI generatedCivil Code provisions on interest calculation; the court held that interest on overdue installments begins running from the date specified in the amended judgment rather than the earlier date originally claimed.
Keywords
AI generatedCited Legislation
AI generatedFull text
Sygn. akt III Ca 823/16
WYROK W IMIENIU
RZECZYPOSPOLITEJ POLSKIEJ Dnia 20 lipca 2016 r. Sąd Okręgowy w Łodzi, III Wydział Cywilny Odwoławczy w składzie następującym: Przewodniczący SSO Krzysztof Kacprzak Sędziowie SO Marta Witoszyńska SR del. Paweł Wrzesiński Protokolant Monika Bura po rozpoznaniu w dniu 20 lipca 2016 roku w Łodzi na rozprawie sprawy z powództwa M. K. i P. K. przeciwko Towarzystwu (...) Spółce Akcyjnej z siedzibą w W. o zapłatę na skutek apelacji pozwanego od wyroku Sądu Rejonowego dla Łodzi Śródmieścia w Łodzi z dnia 8 marca 2016 r., sygn. akt I C 1229/13 I. zmienia zaskarżony wyrok w punkcie 1. w ten sposób, że w miejsce zapisu „przy czym odsetki od rat wymagalnych przed dniem 26 października 2012 roku” ustala, iż odsetki od rat wymagalnych przed dniem 26 października 2013 roku rozpoczynają bieg od tej daty; II. nie obciąża powodów kosztami postępowania apelacyjnego.