Civil court dismisses plaintiff's claim for payment and connection installation, awarding costs to defendant.
Legislator summary
AI generatedThe court dismissed the plaintiff's lawsuit seeking 150,000 PLN and an order to install utility connections. The plaintiff argued for the payment and installation, while the defendant contested the liability. The court rejected the claim, ruling that the plaintiff failed to establish the necessary legal basis for the requested relief.
Legislator headnote
AI generatedArt. 385 § 1 k.p.c.; Art. 386 § 1 k.p.c.: The court dismisses the claim when the plaintiff fails to prove the existence of the legal relationship or the conditions for liability required by the substantive law.
Keywords
AI generatedCited Legislation
AI generatedFull text
Sygn. akt II C 1893/14
WYROK W IMIENIU
RZECZYPOSPOLITEJ POLSKIEJ Dnia 7 lipca 2016 roku Sąd Okręgowy w Łodzi II Wydział Cywilny w składzie: Przewodniczący: S.S.O. T. Jakubowska – Wójcik Protokolant: st. sekr. D. Klimczak po rozpoznaniu w dniu 29 czerwca 2016 r. w Łodzi na rozprawie sprawy z powództwa J. B. przeciwko (...) Spółce Akcyjnej z siedzibą w L. o zapłatę kwoty 150.000 zł i nakazanie wykonania instalacji przyłączeniowej 1. oddala powództwo;
2. zasądza od J. B. na rzecz (...) Spółki Akcyjnej z siedzibą w L. Oddziału Ł. Miasto kwotę 3600 (trzy tysiące sześćset) zł tytułem zwrotu kosztów zastępstwa procesowego.