AI generatedThe court dismissed the plaintiff's lawsuit seeking 4,420.62 PLN in damages against a construction company. The plaintiff alleged non-payment for services rendered, while the defendant argued the work was either not completed or not accepted as specified in the contract. Consequently, the court rejected the monetary claim but ordered the plaintiff to pay 617 PLN in litigation costs.
Legislator headnote
AI generatedUstawa o postępowaniu cywilnym; Ustawa o ochronie prawa autorskiego: The court dismissed the claim for damages when the plaintiff failed to prove the existence of a valid contractual relationship or the specific breach of contract alleged.
Keywords
AI generatedCited Legislation
AI generatedFull text
sygn. akt X GC 438/14
WYROK W IMIENIU
RZECZYPOSPOLITEJ POLSKIEJ Dnia 6 maja 2016 r. Sąd Okręgowy w Łodzi, X Wydział Gospodarczy w składzie: Przewodniczący: SSO Rafał Maciejewski Protokolant: sekr. sąd. Anna Szymańska po rozpoznaniu na rozprawie w dniu 27 kwietnia 2016 r. w Ł. sprawy z powództwa M. O. przeciwko Towarzystwu Budownictwa (...) Spółce z ograniczoną odpowiedzialnością w K. o zapłatę 4.420,62 zł 1) oddala powództwo;
2) zasądza od M. O. na rzecz Towarzystwa Budownictwa (...) Spółki z ograniczoną odpowiedzialnością w K. kwotę 617 zł (sześćset siedemnaście złotych) tytułem zwrotu kosztów procesu.